Starry Research | "Land Purchase and Factory Construction"Series, Issue 2 Classification of Factories in Thailand and Key Points for Construction and Operation
In the previous issue of our 'Land Purchase and Factory Construction' series, we introduced the classification of land and title deeds in Thailand, as well as the eligibility requirements for land purchase. In this issue, we will introduce the classification of factories under Thailand's Factory Act and the key points for their construction and operation.
Competent Authority for Factories
The competent
authority for factories and their operations in Thailand is the Ministry of
Industry and its subordinate Department of Industrial Works (DIW).
Definition of a Factory
Legal Definition of a Factory
Pursuant to
Thailand's Factory Act as amended in 2019, a 'factory' refers to a building,
premises, or vehicle used for carrying out factory operations, where the total
power of machinery used is not less than 50 horsepower or equivalent, or where
not fewer than 50 workers are employed, regardless of whether machinery is
used, and whose type or category is determined in accordance with ministerial
regulations.
Classification of Factories
Factories are
classified into three categories based on their nature: Type 1 Factories, Type
2 Factories, and Type 3 Factories. The operational regulatory requirements for
each category are as follows:
• Type 1 Factory: May commence operations
immediately upon meeting the applicable type, kind, and scale requirements; no
licence application is required.
• Type 2 Factory: Must notify the competent authority in advance before operations
may commence.
•
Type 3 Factory: Must apply for and obtain a
factory licence before construction and operation may begin.
At the same time,
the Ministry of Industry issued ministerial regulations in 2020 classifying
factories into 107 types based on their respective business activities. Each
type of factory is assigned to a corresponding factory category according to
indicators such as the power of machinery used and the number of employees, and
is subject to the corresponding regulatory measures.
For example, a
factory engaged in the processing of tea leaves or tobacco leaves that uses
machinery not exceeding 75 horsepower is classified as a Type 2 Factory; if it
uses machinery exceeding 75 horsepower, it is classified as a Type 3 Factory
and must obtain a factory licence before construction and operation may
commence.
Requirements and Licences for Factory
Construction
Land Use Restrictions (Urban Planning and
Industrial Zones)
The land intended
for factory construction must not contravene applicable legal requirements. For
instance, the land use must comply with the city master plan or specific plans,
the intended use must be consistent with the nature of the land, construction
is not permitted in areas where factories are prohibited or in pollution
control zones, and construction is not permitted in special-purpose areas
designated under other laws (such as environmental law).
Documents
and Licences Required for Factory Construction
Before commencing
construction of a Type 3 Factory, a Factory Licence (RorNgor.4) must be
obtained. The specific application documents and application procedures are as
follows:
To establish a
Type 3 Factory, an application must be submitted using Form
'RorNgor.3' (Factory Establishment Permit Application). Upon approval, the
Director of the Department of Industrial Works or the Provincial Industrial
Works Office will issue the 'RorNgor.4' Factory Operating Licence.
The list of
application documents is as follows:
• Factory Establishment Permit Application Form
(RorNgor.3) – 2 copies;
• Power of attorney (if applicable);
• Copy of national ID card/household registration
for natural persons, or certificate (affidavit) of company for legal entities;
• Factory layout plan, building structural
drawings, and machinery and equipment layout drawings;
• Building permit and land title documents;
• For Type 3 Factories, an Environmental Impact
Assessment report (EIA) must be submitted;
• Other relevant documents depending on the type
of factory.
Detailed Procedure and Timeline for Obtaining a
Factory Licence
Overall processing time: 15 working days (for
reference only; actual time depends on the completeness of the documents, the
category of factory business, and other approval considerations)
|
No. |
Process Step |
Time Required |
|
1 |
Document Review – The applicant submits
the Factory Establishment Permit Application Form (RorNgor.3) and supporting
documents. The receiving officer verifies whether all submitted documents are complete and correct,
and meet the listed documentary requirements. |
1 Working Day |
|
2 |
Engineering and Legal Review – Upon
receipt of the permit application, the reviewing officer will examine the
documents for engineering compliance and legal conformity. Once the review is
completed, the responsible officer will prepare a report and relevant
documents and submit them to the authorised signatory in accordance with the
approval hierarchy. |
12 Working Days |
|
3 |
Signing and Approval – The authorised
person signs the Factory Licence (RorNgor.4) in accordance with the approval
hierarchy and notifies the applicant of the outcome. |
2 Working Days |
In the event of a
rejection, the applicant may appeal to the Director of the Department of
Industrial Works within 30 days of receiving the notification.
Preparation and Operational Start-Up after
Factory Construction Completion
Notification Procedure Prior to Formal
Operations
After the completion of construction, a Type 3
Factory must submit a 'Notice of Commencement of Operations' to the Department
of Industrial Works or the Provincial Industrial Works Office within the
prescribed time period.
• Application deadline: The application must be
submitted within the time specified in the Factory Establishment Permit
Application Form (RorNgor.3) or the Factory Licence (RorNgor.4).
• Notification timing requirement: There must be
an interval of not less than 15 days between the date of notification and the
actual commencement date.
•
If operations cannot commence as scheduled: An
extension must be applied for; otherwise, the licence may be revoked.
If the factory is not yet ready to commence
operations, an extension of time to submit the commencement notice must be
applied for; failure to do so may constitute grounds for revocation of the
factory licence. However, the company may apply to conduct machinery test runs.
Each test run, including the first and all subsequent ones, must not exceed 60
days, and relevant information must be reported as required, including the
start date of the test run, the amount of energy consumed, raw materials used,
and products produced.
Application and Requirements for Machinery Test
Runs
Before conducting machinery test runs, a Type 3
Factory must submit an application to the Department of Industrial Works or the
Provincial Industrial Works Office.
•
Application location:
•
Bangkok area: Department of Industrial Works;
•
Other areas: the Provincial Industrial Works
Office of the relevant province;
•
Test run duration: Not exceeding 60 days;
extension may be applied for;
•
Data to be reported: Start date of the test run,
amount of energy consumed, raw materials used, and products produced, etc.;
•
Recording obligations: Test run data must be
recorded in the prescribed forms of the Department of Industrial Works for
future inspection.
Notification of Business Activities for Type 2
Factories
For Type 2 Factories, a notification must be
filed before commencing business activities, by submitting the notification
application materials to the Department of Industrial Works or the relevant
Provincial Office.
Document
requirements:
(1) Factory Business Activity Notification
Application Form (RorNgor.1) – 2 copies;
(2)
Power of attorney (if applicable);
(3) Copy of national ID card/household registration
for natural persons, or certificate (affidavit) of company for
legal entities;
(4) Factory layout plan, building structural
drawings, and machinery and equipment layout drawings;
(5)
Building permit and land title documents;
(6)
Other relevant documents depending on the type
of factory.
Processing time: can be completed on the
same day of application.
Procedural steps: The receiving officer reviews the Factory Business Activity Notification Application Form (RorNgor.1) and supporting documents to verify whether all submitted documents are complete and correct and meet the listed documentary requirements, after which the receiving officer will issue the Notification Certificate (RorNgor.2).
Other Matters to Note
• After a factory commences operations, an annual
licence fee must be paid each year.
• If a factory needs to add equipment, change its production line, expand its scale, or make similar changes, the relevant notification procedures must be followed or a new licence application must be submitted.